Scheduled for Monday 18th October 2021 at 09:00 (Amsterdam)
Schedule/description of work
Upgrading Merlin openstack version and performing other maintenance. We plan to do this without any downtime or effects for our customers, but some service interruptions may occur.
All of our planned maintenance for this session has been completed successfully. if there are any problems, please do not hesitate to contact us at hpc at rug dot nl.
We have moved Ceph storage backend traffic to its own dedicated networking infastructure, there may have been a short interruption but it should not have cause any problems
The cloud is now updated to wallaby. There was an issue with the nova api services that has been resolved.
After some adjustments Victoria seems to be running more stable than the ussuri installation did. The upgrade to Wallaby has been started. Again, some interruptions in the user interface are to be expected.
We're upgraded to Victoria but we're still seeing some of the same instability in the management environment we saw on Ussuri. We want to look into this some more before we continue to upgrade to Wallaby. We will keep you informed through this page.
We're restarting some of the Liqid infrastructure, this could affect machines running on the Liqid compute nodes